Contract Value £1m
Moreton
The Moreton Terrace vent shaft upgrade is part of the Cooling the Tube Programme upgrade of the entire mid tunnel ventilation shafts on London Underground Victoria Line. The project involved the removal of the existing ventilation system which had a capacity of 37.8m3/s, and the installation a new ventilation system with a capacity 75.6m3/s.

VVB were appointed by Costain to project manage the M&E requirements of the contract from a RIBA Stage D design through installation, commissioning and asset handover of the finished project.

Our role included:

  • Controls and Electrical Design
  • Mechanical Design for Installation
  • M&E Design Coordination and Integration
  • LUL ED Assurance
  • Management of Specialist Subcontractors and Suppliers
  • Installation and Maintenance of Temporary Site Services
  • M&E Installation
  • M&E Testing and Commissioning

Throughout the design and preconstruction phase VVB provided technical knowledge and experience to all elements of the M&E systems and liaised with civil designers to produce a complete integrated solution.

Our scope included:

  • Shaft Ventilation
  • LV Distribution
  • SCADA & Control Systems
  • Building and Shaft Lighting
  • UPS systems
  • Ventilation
  • Fire Detection
  • Temporary Construction LV distribution
  • Interface with Civil and Builders Work